Novin Simia was actively involved in rehabilitation and re-construction of Shindand Airbase since April 2008, working as the electrical sub-contractor with multiple General Contractors both Internationals and Nationals.

Task Orders 1 to 5

Another example of project experience of Novin Simia in power distribution tasks is the implementation of 17 km MV underground grid along with 18 set compact transformer station. Novin Simia was the electrical subcontractor to KAM Construction (General Contractor) in order to complete this task order for the project which was funded by US Army Corps of Engineers. The completion of this project was very important to provision and enhancement of the security to one of the key tactical air base facilities in Afghanistan. The Client – US Army Corps of Engineers – put this news in its website as turning over a milestone project. “Our mission is to turn projects over and it is always a great thing to cut a ribbon on a facility with the quality products that were produced here,” Mathew Walden, resident engineer and contracting officer for the project told the audience gathered for the ceremony at one of the site’s guard towers.

  • 56 Set Compact Transformer Stations
  • 42 km MV Underground Cable
  • 11 km LV Underground Cable
  • 15 Set Generators installed