History of Novin Simia
Novin Simia’s remarkable journey began in 2008 with its first production facility in Herat, Afghanistan. We’ve since expanded, fueled by strategic investments and collaborations. Key milestones include:
2008: Established first production facility in Herat
2010: Opened second production facility in Kabul
2016: Commenced substation projects
2017: Established test, commissioning and in-house design teams
2019: Inaugurated third and fourth facilities in Kabul
2024: Initiated 500 kV Substation Project (Full EPC)
Today, Novin Simia is a premier EPC contractor and trusted manufacturer in Afghanistan, committed to excellence, innovation, and customer satisfaction.

Start Working in Electrical
Start working in electrical industry of Afghanistan Working on Robat Sangi substation project (2005 to 2008)

Register Novin Simia
Register Novin Simia and steblish manufacturing Facilities

Electrical Works for CTC/PD9
Electrical Works for CTC/PD9, Kabul Sub-Contractor to DynCorp

Electrical Works for Shindand
Novin Simia was actively involved in rehabilitation of Electrical System in Shindand Airbase.

Power Distribution Network
Power Distribution Network in Aino Mina Township, Kandahar for 23000 housing units

Novin Simia manufactured
Novin Simia manufactured 2280 Lno. of LV distribution panels and 4500 no. metering boxes for Distribution Plant for Kabul South West funded by Asian Development Bank.

Novin Simia Successfully completed
Novin Simia Successfully completed works in mjor substations Maiwand and Pushmul substations in SEPS and Pul-e Alam Substations in NEPS

substations in Herat, Kabul, Balkh provinces
Novin Simia will complete major substations in Herat, Kabul, Balkh provinces.

Spun Concrete poles
Novin Simia has established a modern spun concrete pole manufacturing facility at Sanaya Sabz Industrial Parks, located in the Deh Sabz district of Kabul.

ANA AEI Electrical Interconnect Construction Project
Design, construction, supply, installation, testing and commissioning of 39.09 km 20 kV Power Distribution Line (27.81 km Double Circuit & 11.28 km Single Circuit).

Dasht-e-Alwan Substation
500/220/20 kV substation with incoming line bay, 2x100 MVAR shunt reactor bays.Client: Da Afghanistan Breshna Sherkat (DABS)

Kandahar Breshnakot Substation
110/20 kV line bay extension with transfer bay and outgoing feeders. Client: Da Afghanistan Breshna Sherkat (DABS)

Kunduz Transmission Line
Extension of a new 220 kV Transmission Line with a length of 44.5 Km from Asqalan Substation to a new Substation in Dasht-e-Archi District of Kunduz Province, including Survey, Design, Procurement of Equipment, Installation, Testing and Commissioning.

3 Substations in Qarabagh, Moqor & Shahjoy
Completion of Design, Supply, Installation, Construction and Testing and Commissioning of Qarabagh, Moqor and Shah Joy 220 KV/20KV Substations (One Lot)

4 Substations in Herat
Construction, Erection, Testing and Commissioning of 4 Nos Of 110/20 kV Substations Each at Karokh, Chesht, Hobai, Pashtoon-Zarghoon Project